Alpine Better Places Project - Bright

"Mafeking Square, Bright - The Heart of the Town"

To download a copy of the history of Mafeking Square, "Mafeking Square, Bright - The Heart of the Town" click here. Many thanks to the Bright RSL Sub-branch for compiling this document.

Mafeking Precint, Friday, 24 February 2017 Project Update

The Mafeking Square Precinct Upgrade works are now progressing well, please note the following advice with regard to the project. Once again, we thank you for your patience, as we appreciate that these works are highly disruptive.

ROAD CLOSURE – Friday, 3 March 2017
We advise that Ireland Street (between Cobden and Camp Streets) and the south bound lane of Anderson Street (between Wood Street and the roundabout) will be closed Friday, 3 March between 6 and 9 am to enable trenching to occur across the road in two locations within the roundabout. Traffic diversions will be in place during the closure.

Traffic movements which exit north into Anderson Street, via the roundabout from Burke Street will remain open. Barnard Street to Camp Street will also remain open. All lanes will be re-opened by 9 am.

EAST MAFEKING
The issues with services have now been resolved and we have been able to progress works in the area on the east side of Ireland Street, between the NAB and the Op Shop (Shop 26). We are working on this area as a priority and are aiming to complete the majority of the footpath and kerb works by the end of next week.

IRELAND STREET – NORTH BOUND
The newly aligned north bound traffic lane is now in place. Asphalting of this surface will take place later in the program when all other road surfaces are paved, so in the meantime, please take care when driving on this gravel surface.

Demolition and construction works will continue behind the new kerb in the vicinity of the Uniting Church in the coming weeks.

ROUNDABOUT
Construction of the area inside the roundabout is continuing. Demolition of the surfaces is largely complete and the stone wall seating and electrical works have commenced.

WEST MAFEKING
The works on the west side of Mafeking Square between JD’s Ski Shop and Bright Escapes will not commence prior to the Labour Day weekend (11-13 March). Some isolated service works may be undertaken in the coming fortnight, however disruption will be minimal and any disturbed surfaces will be temporarily reinstated.

Traffic and pedestrian management will continue to be in place to control access to the shops, so for your own safety, please comply with all signage and do not enter the construction areas.

There will be increased noise, heavy vehicle traffic, disruptions and detours in the Bright town centre throughout the duration of the works. We anticipate that the works will be complete by Easter 2017. We encourage you to park in the Burke Street, Wills Street and Senior Citizens Centre off street car parks for the duration. We will provide regular project updates via email, our Facebook page and website.

We understand these works will cause inconvenience and thank you for your patience during this time.

Mafeking Precinct, February 2017 Project Update

The Mafeking Square Precinct Upgrade works are well underway. We thank you for your patience, as we appreciate that these works are highly disruptive.

IRELAND STREET – NORTH BOUND LANE
In the coming fortnight the contractor will continue in the centre median of Ireland Street, with the aim of opening up the newly aligned north bound traffic lane by the end of next week. This work will require the temporary deviation of this traffic lane onto the footpath towards the Uniting Church, as shown in the attached image. During the temporary deviation, traffic will be slowed to 20 km/hr, so please travel slowly and obey all road signage.

This deviation should not be used by high or long vehicles such as buses, caravans and large trucks. Large vehicles will be detoured down Railway Avenue or Cobden and Wills Street. Please also note that the north bound lane will be closed between 7 am and 10 am on Monday morning, so that the temporary deviation measures can be put in place.

ROUNDABOUT
Demolition and construction of the area inside the roundabout has commenced and will be ongoing over the next fortnight.

EAST MAFEKING
There have been some unforeseen delays in the area on the east side of Ireland Street, between the NAB and the Op Shop (Shop 26), due to complications with existing services. This component of the works is therefore slightly delayed.

Traffic and pedestrian management will continue to be in place to control access to the shops, so for your own safety, please comply with all signage and do not enter the construction areas.

There will be increased noise, heavy vehicle traffic, disruptions and detours in the Bright town centre throughout the duration of the works. We anticipate that the works will be complete by Easter 2017. We encourage you to park in the Burke Street, Wills Street and Senior Citizens Centre off street carparks for the duration. We will provide regular project updates via email, our Facebook page and website.

We understand these works will cause inconvenience and thank you for your patience during this time.

Mafeking Precinct, December 2016 Project Update

Council is pleased to advise that award of the Mafeking Square Precinct landscape and civil works construction contract was approved at the December Council meeting to experienced contractors Excell Gray Bruni. The project can therefore commence on Monday, 30 January 2017 as planned, with the aim of being completed by the Easter long weekend 2017.

Public Information sessions were held on December 13, 2016. You can access the presentation, which contains the proposed construction staging plans, here.

You can also download the latest finishes plan here. This plan reflects the intent of the works and is provided for information purposes only. Please note that there may be some variations to the works during construction, which will result in differences between the constructed works and those detailed on this plan.

If you have any concerns regarding the works or the proposed construction staging, please contact the Project Manager Francine Stacey on 5755 0567 or 0437 222 439, or via email at francines@alpineshire.vic.gov.au.

Mafeking Square Precinct, November 2016 Project Update

On Monday, 31 October, the Hume Regional Director of Regional Development Victoria, Matt Nelson, visited Bright to announce that the Bright Alpine Better Places Project has received a $500,000 funding injection from the State Government. This funding has been made available through the Victorian Government’s Regional Jobs and Infrastructure Fund and is a very significant and welcome contribution to the project.

Since August, the following works have been completed or are underway:
- Documentation of the Bright, Stage 1 landscape and road works
- Tendering of the landscape and road works
- Tendering of the custom made street furniture
- Stakeholder and authority engagement

We are still aiming to award the contracts for the landscape and road works, as well as the custom made street furniture in early December 2016. At that time we will have a preliminary construction program, so it is our intention to hold an information session in December to seek feedback on the proposed program and to present the plans for construction. It is still anticipated that the majority of the construction works will occur in February and March 2017.

Mafeking Square Precinct, August 2016 Project Update

In July 2016 Council adopted a budget of $1,440,000 (Grants $476,000 & Alpine Shire Contribution $964,000) to undertake the Bright (Stage 1) – Mafeking Square Precinct works. Work has commenced with the following already completed or underway:
- Design consultants appointed to document Bright, Stage 1 & Porepunkah works
- Subsurface utility location & mapping
- Arboricultural reporting
- Geotechnical investigations & reporting
- Heritage investigations
- Stakeholder & authority engagement commenced
On the 28th July a drop-in and public information session was held and the presentation can be downloaded here.

We are currently working to complete documentation of the works in order to tender the construction works later this year. At this stage it is anticipated that the majority of the construction works will occur in February and March 2017.

Detailed Concept Designs

Alpine Better Places

Council commenced its Alpine Better Places project in early 2015, with the aim of delivering detailed concept designs for priority projects in each of the town centres of Porepunkah, Bright and Myrtleford. The project progressed well through its first three phases including two rounds of community consultation. Council and community input was sought in March to prioritise projects in each of the townships. Council and community feedback was then sought on the preliminary concept designs in June and their visions for each town have been included on the draft detailed concept designs.

The proposed streetscape improvements were outlined in the Draft Detailed Concept Designs which went on public exhibition in late 2015. At the March 2016 Council Meeting, following consideration of all comments and submissions received, Council determined to adopt both the recommended responses to the formal submissions and the Final Detailed Concept Designs for Myrtleford, Porepunkah and Bright, completed under Alpine Better Places.

The de-identified submission summaries and decisions can be viewed under the 2016 Council meeting agendas and minutes, 1 March 2016 - Ordinary Council Meeting. The Final Detailed Concept Designs can also be downloaded here:

Bright

Myrtleford

Porepunkah

If you have any queries about the Alpine Better Places project please contact Project Manager Francine Stacey on (03) 5755 0555 or francines@alpineshire.vic.gov.au